Utility says power lines for Keystone pipeline won't be done in 2014

2013-02-18T05:30:00Z 2013-06-25T17:48:19Z Utility says power lines for Keystone pipeline won't be done in 2014The Associated Press The Associated Press
February 18, 2013 5:30 am  • 

COLUMBUS, Neb. — A Nebraska utility says the new route for a proposed oil pipeline that would carry Canadian crude oil through the state will delay work on electric transmission lines for the pipeline.

Nebraska Public Power District officials said they won't be able to build the transmission lines by the deadline TransCanada set for the end of 2014.

NPPD Chief Operating Officer Tom Kent said there's no way the transmission lines will be ready by 2015.

"We have a lot of work to do," he said.

TransCanada's proposed Keystone XL pipeline will carry Canadian crude to the Gulf Coast if it can win President Barack Obama's approval. The proposed $7 billion pipeline would cross Montana, South Dakota, Nebraska, Kansas, Oklahoma and Texas. TransCanada also has proposed connecting it to the Bakken oil field in Montana and North Dakota.

The southern section of the pipeline between Oklahoma and the Gulf Coast is already under construction, but TransCanada needs a presidential permit for the northern section because the pipeline crossed the U.S.-Canadian border.

TransCanada altered the pipeline's proposed path through Nebraska last year to avoid the environmentally sensitive Sandhills region and a couple towns' drinking water wells. Nebraska Gov. Dave Heineman recently signed off on the new route.

That new route forces NPPD to redo design and planning work for all the areas where the pipeline route changed. Officials estimated that could take 12 to 24 months to complete.

NPPD expects to spend $44 million on the transmission lines, but TransCanada will have to reimburse the utility regardless of whether the pipeline is ultimately built.

Environmentalists oppose the project because they worry the pipeline could contaminate groundwater reserves and threaten ecologically sensitive areas in Nebraska and other states along its 1,700-mile path.

Thousands of people attended a protest in Washington, D.C., on Sunday to urge Obama to reject the pipeline. The crowds marched from the National Mall to the White House.

Pipeline backers say the project will create thousands of jobs both in the construction of the pipeline and at refineries. Opponents say the pipeline won't create nearly as many jobs as TransCanada has projected.

Project supporters also say the project would give the United States a steady source of oil from a friendly neighboring country.

Copyright 2015 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

More from the Gazette

Montana youth court officer charged with raping teen

10 hours agoLoading…
Citing lack of support, McCulloch drops vote by mail bill

Citing lack of support, McCulloch drops vote by mail bill

10 hours ago Photos

Photos

Loading…
Woman scammed while trying to purchase monkey online

Woman scammed while trying to purchase monkey online

14 hours agoLoading…
2 charged in theft from Cathedral of St. Helena

2 charged in theft from Cathedral of St. Helena

14 hours ago Photos

Photos

Loading…
Helping young kids with sexual behavior problems

Helping young kids with sexual behavior problems

16 hours agoLoading…

Montana man convicted of elder abuse

17 hours agoLoading…

Follow The Billings Gazette

Popular Stories

Get weekly ads via e-mail

Deals & Offers

Featured Businesses